Waste treatment plant Tibro

Reningsverk Tibro Coverto

PROJECT DESCRIPTION

Client:  Asplunds Bygg
Location:  Tibro, Sweden
Area:  12 000 m2
Completed:  2022
Description:  Coverto has been enthrusted to deliver and install high-profile roofing sheet (TRP) also knows as decking profiles, concrete plinth, steel stairs and sandwich panels with accessories for the treatment plant in Tibro, Västra Götaland.

One of the new facilities contains filter steps that clean all the water that is released.

The second facility is for receive filtering. At the beginning of 2023, the construction is expected to be completed, and then Tibro will have a treatment plant that both cleans better than today and that can also cope with an expected increase in population for a long time to come.

Snabbgross

Snabbgross Coverto

PROJECT DESCRIPTION

Client:  Asplunds Bygg
Location:  Skövde, Sweden
Area:  approx. 1 800 m2
Completed:  2022
Description:   Coverto was enthrusted to design, deliver and install steel frame, trusswork, roof incl. roof covering, concrete plinth, steel frame for mezzanine, sandwich panels with accessories and a canopy.

The main customer wanted an entrance portal that had a smooth surface, long span of 10 m, hidden fastening, no visible vertical joints/fittings, special color and that the sandwich panels would be aligned with the existing facade.

We solved this with a cost-effective special solution together with our suppliers. The solution is unique and something we take with us as an offer in other projects.

Steel hall Sävsjö

Coverto TRP Sävsjö bärplåt

PROJECT DESCRIPTION

Client:  AAAB
Location:  Sävsjö, Sweden
Area: 1 000 m2
Completed:  2021
Description: Coverto was entrusted to supply high-profile roofing sheet (TRP) also known as decking profiles with associated accessories, fittings and fasteners for a steel hall project in Sävsjö, Jönköping.

Waste treatment plant Skillingaryd

image_2022_10_14T07_24_56_396Z

PROJECT DESCRIPTION

Client:  HMTAB
Location:  Skillingaryd, Jönköping
Area:  270 m2
Completed:  2021
Description:  Coverto was entrusted with supplying mineral wool sandwich panels with associated accessories, fittings and fasteners to the treatment plant in Skillingaryd, Jönköping.

Ebrex

IMG_5034

Project Description

Client:   Logistic Contractor
Location:   Örebro, Sweden
Area:   12 000 m2
Completed:   2019
Description:   Logistic Contractor developed a new warehouse for British Ebrex for Ford’s spare parts in the autumn of 2018. Coverto has carried out the installation the exterior sandwich panels, roof drainage, sheet metal work and steel stairs.

ICA

23#

Project Description

Client:   Skanska
Location:   Gothenburg, Sweden
Area: 1500 m2
Completed:   2017
Description: Coverto delivered sandwich walls to a new ICA Kvantum, built by Skanska.

Media Markt

18.

Project Description

Client:   Skanska
Location:   Gothenburg, Sweden
Area: 380 m2
Completed:   2016
Description: Media Markt needed to reduce its retail space. Coverto delivered and installed 2 parallel vertical sandwich walls with a safety class II and one air gap between them to cope with the sound requirements while ongoing trading was ongoing. Good planning and risk analysis was required in order to perform efficient work in 3 weeks.

Kungsmöbler

12

Project Description

Client:   NB Bygg
Location:   Jonkoping, Sweden
Area: 350 m2
Completed:   2015
Description: Coverto delivered all exterior sandwich walls (including flashings and fasteners) to the new warehouse of furniture store Kungsmöbler.

ABB

11

Project Description

Client:   Ronneby Svets&Smide
Location:   Verkö, Sverige
Area: 140m2
Completed:   2015
Description: ABB needed to new cladding system for a refrigeration center. Coverto delivered sandwich walls in mineral wool with flashings and fasteners for assembly by the customer.

Scania

10

Project Description

Client:   Skanska
Location:   Oskarshamn, Sweden
Area: 15,000 m2
Completed:   2014
Description: Coverto supplies sandwich walls to Scania’s new body workshop and logistic warehouse in Oskarshamn. It is important to make the buildings energy-efficient. This involves care when selecting materials and products that are part of the construction process as well as high quality in performance to ensure low energy consumption.